[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256545":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256545,840,2,"多选题","编制施工进度图的依据有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计图纸",true,{"key":16,"text":17,"correct":14},"B","自然调查条件",{"key":19,"text":20,"correct":21},"C","预算文件",false,{"key":23,"text":24,"correct":14},"D","劳动力供应情况",{"key":26,"text":27,"correct":14},"E","合同规定开工、竣工日期","ABDE","编制施工进度图的依据有设计图纸、自然调查条件、劳动力供应情况、合同规定开工、竣工日期。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]