[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256544":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256544,840,2,"多选题","施工过程的单位可大可小，可以是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分项工程",true,{"key":16,"text":17,"correct":18},"B","整个施工项目",false,{"key":20,"text":21,"correct":14},"C","单位工程",{"key":23,"text":24,"correct":14},"D","分部工程",{"key":26,"text":27,"correct":18},"E","单项工程","ACD","施工过程的单位可大可小，可以是分项工程、单位工程、分部工程。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]