[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256541":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256541,840,2,"多选题","若某项工作比原计划拖后，当拖后的时间小于其拥有的总时差时，则（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","不影响其后续工作和工程总工期",false,{"key":16,"text":17,"correct":14},"B","不影响其后续工作，但影响总工期",{"key":19,"text":20,"correct":14},"C","影响其后续工作且影响工程总期",{"key":22,"text":23,"correct":24},"D","影响后续工作最迟开始时间",true,{"key":26,"text":27,"correct":24},"E","影响其后续工作但不影响工程总期","DE","若某项工作比原计划拖后，当拖后的时间小于其拥有的总时差时，则影响后续工作最迟开始时间、影响其后续工作但不影响工程总期。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]