[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256540":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256540,840,2,"多选题","桥梁施工中，有些施工顺序不受固定顺序的限制是指如（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钻孔灌注桩和桥墩的施工顺序",false,{"key":16,"text":17,"correct":18},"B","上部结构预制与下部结构施工顺序",true,{"key":20,"text":21,"correct":18},"C","整个桥梁施工是从一岸向另一岸推进，还是从两岸向中间推进",{"key":23,"text":24,"correct":18},"D","先施工水中基础还是先施工岸边基础或两者同时进行",{"key":26,"text":27,"correct":14},"E","后张法预应力张拉与混冱土浇筑","BCD","上部结构预制与下部结构施工顺序、整个桥梁施工是从一岸向另一岸推进，还是从两岸向中间推进、先施工水中基础还是先施工岸边基础或两者同时进行等施工顺序不受固定顺序的限制。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]