[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256539":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256539,840,2,"多选题","施工阶段进度控制的具体措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","安全措施",false,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","合同措施",{"key":26,"text":27,"correct":14},"E","技术措施","ACDE","施工项目进度控制的措施进度控制的措施包括组织措施、技术措施、经济措施和合同措施等。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]