[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256538":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256538,840,2,"多选题","在编制单位工程施工进度计划时，应包括的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工段落划分",true,{"key":16,"text":17,"correct":14},"B","施工顺序确定",{"key":19,"text":20,"correct":14},"C","施工机具选择",{"key":22,"text":23,"correct":24},"D","施工组织机构",false,{"key":26,"text":27,"correct":24},"E","专项方案确定","ABC","单位工程施工进度计划的内容包括：施工段落划分、施工顺序确定、施工机具选择等。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]