[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256536":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256536,840,2,"多选题","施工进度计划检查完成后，应向企业提供施工进度报告，报告应包括的内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","劳务记录及预测",true,{"key":16,"text":17,"correct":18},"B","计划施工进度图及简要说明",false,{"key":20,"text":21,"correct":18},"C","待解决的问题",{"key":23,"text":24,"correct":14},"D","工程变更",{"key":26,"text":27,"correct":14},"E","索赔及工程款收支情况","ADE","进度报告主要内容应包括：报告的起止日期；当地气象及晴雨天数统计；施工计划的原定目标及实际完成情况；报告计划期内现场的主要大事记（如停水、停电、发生事故的概况和处理情况，收到建设单位、监理工程师、设计单位等指令文件及主要内容）；实际施工进度图；工程变更，价格调整，索赔及工程款收支情况；进度偏差的状况和导致偏差的原因分析；计划调整意见和建议。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]