[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256534":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256534,840,2,"多选题","关于双代号网络计划的说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可能没有关键线路",false,{"key":16,"text":17,"correct":18},"B","至少有一条关键线路",true,{"key":20,"text":21,"correct":18},"C","当计划工期等于计算工期时，关键工作为总时差为零的工作",{"key":23,"text":24,"correct":14},"D","在网络计划执行过程中，关键线路不能转移",{"key":26,"text":27,"correct":14},"E","由关键节点组成的线路是关键线路","BC","双代号网络图是用一对节点及之间的箭线表示一项工作的网络图。其中的节点（圄圈）表示工作间的连接（工作的开始结束）。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]