[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256533":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1256533,840,2,"多选题","在编制某市政工程施工进度计划时，主要包括的内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","各施工项目的工程量",true,{"key":16,"text":17,"correct":14},"B","劳动量或机械台班量",{"key":19,"text":20,"correct":14},"C","工作持续时间",{"key":22,"text":23,"correct":14},"D","施工班组人数及施工进度",{"key":25,"text":26,"correct":27},"E","人员素质",false,"ABCD","施工进度计划内容包括：各施工项目的工程量、劳动量或机械台班量、工作持续时间、施工班组人数及施工进度等。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)专业管理实务 岗位知识","建筑工程",0]