[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256530":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},1256530,840,2,"多选题","分段不分层时无间歇时间的等节拍专业流水的施工工期计算公式正确的是（ ）。",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",false,{"key":20,"text":20,"correct":18},"D",{"key":22,"text":22,"correct":13},"E","ABE","分段不分层时无间歇时间的等节拍专业流水的施工工期计算公式包括：T=∑ki，j+1+mt、T=(n—1)XK+mt、T=∑ki，j+1+m×j×t。",{"id":6,"name":26,"category":27,"favorite":28},"(市政施工)专业管理实务 岗位知识","建筑工程",0]