[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256524":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256524,840,1,"单选题","市政工程的竣工验收，应由（ ）项目负责人组织参建各方单位项目负责人进行单位工程验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","监理单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","质量监督单位","市政工程的竣工验收，应由建设单位项目负责人组织参建各方单位项目负责人进行单位工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]