[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256485":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256485,840,1,"单选题","按照建设工程项目目标划分，信息的分类有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目内部信息和外部信息",false,{"key":16,"text":17,"correct":14},"B","生产性、技术性、经济性和资源性信息",{"key":19,"text":20,"correct":14},"C","固定信息和流动信息",{"key":22,"text":23,"correct":24},"D","投资控制、进度控制、质量控制信息及合同管理信息",true,"按照建设工程项目目标划分，信息的分类有投资控制、进度控制、质量控制信息及合同管理信息。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]