[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256478":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256478,840,1,"单选题","工程量清单漏项或设计变更引起的新的工程量清单项目，其相应综合单价由（ ）提出，经确认后作为结算的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","设计单位","因工程量清单漏项或非承包人原因的工程变更，造成增加新的工程量清单项目，合同中没有适用或类似综合单价，由承包人提出综合单价，经发包人确认后执行。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]