[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256477,840,1,"单选题","下列关于施工成本控制的步骤，正确排序的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","比较→预测→分析→纠偏→检查",false,{"key":16,"text":17,"correct":14},"B","预测→比较→分析→纠偏→检查",{"key":19,"text":20,"correct":14},"C","预测→分析→纠偏→检查→比较",{"key":22,"text":23,"correct":24},"D","比较→分析→预测→纠偏→检查",true,"施工成本控制的步骤：比较→分析→预测→纠偏→检查。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]