[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256474,840,1,"单选题","下列有关工程量计算的论述中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","土方开挖体积应按挖掘前的天然密实体积计算",false,{"key":16,"text":17,"correct":14},"B","挖方出现流沙时，如设计未明确，结算时，应根据实际情况由发包人与承包人双方现场签证确认工程量",{"key":19,"text":20,"correct":21},"C","计算开挖沟槽断面体积时，若存在不同类别土壤时，应分别按放坡起点、放坡系数，依不同土类别厚度取算术平均值计算",true,{"key":23,"text":24,"correct":14},"D","管沟施工每侧所需工作面宽度取值与管道结构宽有关","计算开挖沟槽断面体积时，若存在不同类别土壤时，应分别按放坡起点、放坡系数，依不同土类别厚度加权平均值计算。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]