[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256471,840,1,"单选题","在施工成本计划的编制程序中，按照（ ），计算各分部分项工程的计划人工、材料、机械使用量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工方案",false,{"key":16,"text":17,"correct":14},"B","预控偏差总和",{"key":19,"text":20,"correct":21},"C","企业施工定额",true,{"key":23,"text":24,"correct":14},"D","市场生产要素价格信息","在施工成本计划的编制程序中，按照企业施工定额，计算各分部分项工程的计划人工、材料、机械使用量。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]