[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256463,840,1,"单选题","某城市道路全长640m，路面宽度为12m，路肩宽度为1m，由于该段地基湿软，对其进行碎石桩处理。前后桩间距8m，路基宽度范围内一排3根桩，桩径为0.5m，桩长为2m。根据工程量清单计算规则，则该碎石桩的工程量为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","162m",false,{"key":16,"text":17,"correct":14},"B","432m",{"key":19,"text":20,"correct":14},"C","456m",{"key":22,"text":23,"correct":24},"D","486m",true,"（640\u002F8+1）*2*3=486",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]