[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256462,840,1,"单选题","下列措施中，不属于施工成本目标控制的方法是的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以目标成本控制成本支出",true,{"key":16,"text":17,"correct":18},"B","合理配置施工人员",false,{"key":20,"text":21,"correct":18},"C","用净值法进行工期成本的同步控制",{"key":23,"text":24,"correct":18},"D","运用目标管理控制工程成本","施工成本目标控制的方法包括：合理配置施工人员；用净值法进行工期成本的同步控制；运用目标管理控制工程成本。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]