[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256456,840,1,"单选题","下列选项中，不属于施工项目成本中的直接成本的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":14},"B","材料费",{"key":19,"text":20,"correct":21},"C","工程排污费",true,{"key":23,"text":24,"correct":14},"D","文明施工及环境保护措施费","直接成本包括：人工费、材料费、机械使用费、措施费。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]