[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256447,840,1,"单选题","A公司中标的某城市场高架跨线桥工程，为15跨25m预应力简支梁桥，桥面宽22m，采用?1200mm的钻孔灌注桩基础，埋置式承台，Y型独立式立柱。工程中标价2850万元。经过成本预测分析，项目目标成本为2600万，其中间接成本占10％。在工程进行过程中发生了如下事件：事件1.工程开工2个月后，因资金不足，贷款500万元，共支付利息30万元。事件2.某承台开挖时发现文物，按上级有关部门要求停工30d，导致总工期拖延10d，未发生直接成本损失。 下列选项中，不属于成本控制的依据的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同文件",false,{"key":16,"text":17,"correct":14},"B","施工成本计划",{"key":19,"text":20,"correct":14},"C","工程变更",{"key":22,"text":23,"correct":24},"D","施工进度计划",true,"施工成本控制的依据包括以下内容：（1）工程承包合同（2）施工成本计划（3）进度和施工统计报告（4）工程变更（5）有关的施工组织设计、分包合同等也都是施工成本控制的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]