[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256444,840,1,"单选题","下列关于施工成本控制的施工中，论述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目总工是项目成本管理的第一责任人",false,{"key":16,"text":17,"correct":14},"B","按照全面成本控制原则，应组织项目部各部门负责人参与成本控制",{"key":19,"text":20,"correct":14},"C","压缩生产用工和辅助用工，严格控制生产人员比例",{"key":22,"text":23,"correct":24},"D","合理布置材料的现场堆放和保管，减少二次搬运甩",true,"项目负责人是项目成本管理的第一责任人；按照全面成本控制原则，组织项目部各部门、各岗位人人参与成本控制，真正做到全员、全过程的管理，建立健全项目成本管理体系；压缩非生产用工和辅助用工，严格控制非生产人员比例。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]