[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256399,840,1,"单选题","下列关于施工过程质量验收不合格处理描述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在检验批验收时，发现存在严重缺陷的应推到重做",false,{"key":16,"text":17,"correct":18},"B","在检验批验收时，有一般的缺陷通过反修或更换消除缺陷后，应不做再验收",true,{"key":20,"text":21,"correct":14},"C","严重质量缺陷或超过检验批范围内的缺陷，经法定检测单位检测鉴定以后，认为不能满足最低限度的安全储备和使用功能，则必须进行加固处理",{"key":23,"text":24,"correct":14},"D","通过返修或加固处理后仍不能满足安全使用要求的分部工程严禁验收","施工过程质量验收不合格时：在检验批验收时，发现存在严重缺陷的应推到重做；严重质量缺陷或超过检验批范围内的缺陷，经法定检测单位检测鉴定以后，认为不能满足最低限度的安全储备和使用功能，则必须进行加固处理；通过返修或加固处理后仍不能满足安全使用要求的分部工程严禁验收。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]