[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256391,840,1,"单选题","建设工程项目质量控制的基本方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","三阶段控制原理",false,{"key":16,"text":17,"correct":18},"B","PDCA循环原理",true,{"key":20,"text":21,"correct":14},"C","三全控制管理",{"key":23,"text":24,"correct":14},"D","三完善控制原理","事前控制、事中控制、事后控制三个质量控制阶段不是互相孤立和截然分开的，它们共同构成了一个有机的系统过程，实际上也是质量管理PDCA大循环的具体实践。所以建设工程项目质量控制的基本方法是PDCA循环原理。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]