[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256374,840,1,"单选题","关于路基工程挖土施工安全技术交底的内容，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","路堑边坡设混凝土灌注桩、地下连续墙等挡土墙结构时，应待挡土墙结构强度达设计规定后，方可开挖路堑土方",true,{"key":16,"text":17,"correct":18},"B","在天然湿度土质的地区开挖土方，砂土和砂砾土开挖深度不超过2.0m，可开挖直槽",false,{"key":20,"text":21,"correct":18},"C","在距现状直埋缆线2m范围内采用机械开挖时，应邀请管理单位派人现场监护",{"key":23,"text":24,"correct":18},"D","人工开挖路堑深度大于5m时，应分层开挖，每次高度不得大于3m，层间应留","路基工程挖土施工安全技术交底：路窒边坡设混凝土灌注桩、地下连续墙等挡土墙结构时，应待挡土墙结构强度达设计规定后，方可开挖路整土方；在天然湿度土质的地区开挖土方，砂土和砂砾石开挖深度不超过1.Om、亚砂土和粉质结土开挖深度不超过1.2m、教土开挖深度不超过1.5m时，当地下水位低于开挖基面50cm以下，可挖直槽（坡度为1:0.05）。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]