[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256370,840,1,"单选题","某工程进行检验批验收时，发现某框架梁截面尺寸与原设计图纸尺寸不符，但经原设计单位核算，仍能满足结构安全及使用功能要求，则该检验批（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","必须重新施工",false,{"key":16,"text":17,"correct":14},"B","必须经施工单位和业主协商确定是否予以验收，其经济责任由业主承担",{"key":19,"text":20,"correct":14},"C","必须进行加固处理后重新组织验收",{"key":22,"text":23,"correct":24},"D","可直接予以验收",true,"某工程进行检验批验收时，发现某框架梁截面尺寸与原设计图纸尺寸不符，但经原设计单位核算，仍能满足结构安全及使用功能要求，则该检验批可直接予以验收。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]