[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256338,840,1,"单选题","当排水管道工程发生设计变更时，应由（ ）对技术交底进行修改或补充，经项目技术负责人审批后重新交底。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工员",false,{"key":16,"text":17,"correct":14},"B","质检员",{"key":19,"text":20,"correct":21},"C","原交底人",true,{"key":23,"text":24,"correct":14},"D","技术负责人","当排水管道工程发生设计变更时，应由原交底人对技术交底进行修改或补充，经项目技术负责人审批后重新交底。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]