[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256334,840,1,"单选题","某市政道路桥梁工程施工项目，承包人建立了以项目总工第一责任人的质量管理体系，监理单位也建立了相应的质量建立体系。项目施工完后，报请政府相关机构进行质量验收时，遭受拒绝。 施工项目质量管理体系过程一般可分为工程调研和任务承接、施工准备、材料采购、施工生产以及交工验收和（ ）等八个阶段。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人员管理",false,{"key":16,"text":17,"correct":14},"B","设备采购",{"key":19,"text":20,"correct":14},"C","合同管理",{"key":22,"text":23,"correct":24},"D","回访与维修",true,"施工项目质量管理体系过程一般可分为工程调研和任务承接、施工准备、材料采购、施工生产以及交工验收和回访与维修等八个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]