[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256331,840,1,"单选题","某市政道路桥梁工程施工项目，承包人建立了以项目总工第一责任人的质量管理体系，监理单位也建立了相应的质量建立体系。项目施工完后，报请政府相关机构进行质量验收时，遭受拒绝。 施工单位的项目经理部中质量的第一责任人应是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":18},"B","项目总工",false,{"key":20,"text":21,"correct":18},"C","工程部长",{"key":23,"text":24,"correct":18},"D","质检员","项目经理是施工单位的项目经理部中质量的第一责任人。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]