[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256320":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256320,840,1,"单选题","如果施工中发生工期延误，欲对后续工作的持续时间压缩，错误的做法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","压缩资源有保证的工作",false,{"key":16,"text":17,"correct":14},"B","压缩对质量影响不大的工作",{"key":19,"text":20,"correct":14},"C","压缩对安全影响不大的工作",{"key":22,"text":23,"correct":24},"D","压缩时差最大的工作",true,"施工中发生工期延误，欲对后续工作的持续时间压缩，可以压缩资源有保证的工作、压缩对质量影响不大的工作、压缩对安全影响不大的工作等。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]