[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256318,840,1,"单选题","某基础工程土方开挖总量为8800m3，该工程拟分5施工段组织固定节拍流水施工，两台挖掘机每台班产量定额均为50m3，采用2班制作业，其流水节拍应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","44",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","3","本题考查的是流水施工参数。根据流水节拍定额计算法的公式，t=Q\u002F（S×R×N），即",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]