[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256308,840,1,"单选题","在单代号网络计划中，设H工作的紧后工作有I和J，总时差分别为3天和4天，工作H和I之间时间间隔为8天，工作H和J之间的时间间隔为6天，则工作H的总时差为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5天",false,{"key":16,"text":17,"correct":14},"B","8天",{"key":19,"text":20,"correct":21},"C","10天",true,{"key":23,"text":24,"correct":14},"D","12天","单代号网络计划中，工作的总时差应等于本工作与其各紧后工作之间的时间间隔加该紧后工作的总时差所得之和的最小值（终点节点所代表的工作除外）。因此工作H的总时差为{3+8，4+6}10参见教材127、128该题针对施工管理中的“施工进度计划的编制方法”知识点进行考核",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]