[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256307,840,1,"单选题","当某工程采用的流水施工分段又分层时，对同一施工层，在划分施工段数时，宜（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工段数大于施工过程数",true,{"key":16,"text":17,"correct":18},"B","施工段数等于施工过程数",false,{"key":20,"text":21,"correct":18},"C","施工段数小于施工过程数",{"key":23,"text":24,"correct":18},"D","施工段数小于等于施工过程数","采用的流水施工分段又分层时，对同一施工层，在划分施工段数时，宜施工段数大于施工过程数。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]