[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256306,840,1,"单选题","当单代号网络图中有多项起点节点时，正确的做法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调整多项起点节点的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","合并多项起点节点作为起点节点",{"key":19,"text":20,"correct":14},"C","多项起点节点采用相同的编号",{"key":22,"text":23,"correct":24},"D","设置一项虚工作作为起点节点数量",true,"单代号网络图中有多项起点节点时，只能有一个起点和终点，所以应该设置一项虚工作作为起点节点数量。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]