[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256303,840,1,"单选题","双代号网络计划中的虚箭线是实际工作中并不存在的一项虚设工作，一般起着工作之间的联系.区分和（ ）。个作用。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","交叉",false,{"key":16,"text":17,"correct":14},"B","汇合",{"key":19,"text":20,"correct":14},"C","分流",{"key":22,"text":23,"correct":24},"D","断路",true,"双代号网络计划中的虚箭线表示的工作既不消耗时间又不消耗资源。它只是用来表达工作之间的逻辑关系，一般起着工作之间的联系，区分和断路的作用。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]