[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256301":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256301,840,1,"单选题","组织桥梁大梁预制流水作业时，其工序为支模、扎筋、浇混凝土、拆模、横移堆放。因浇注混凝土后，要等混凝土强度达到要求后，拆移工序才能开始。为此，流水作业中应当考虑（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术间歇",true,{"key":16,"text":17,"correct":18},"B","组织间歇",false,{"key":20,"text":21,"correct":18},"C","平行搭接",{"key":23,"text":24,"correct":18},"D","顺序施工","根据施工过程的工艺性质，在流水施工中除了考虑两个相邻施工过程之间的流水步距外，还需考虑增加一定的工艺或技术间隙时间。如楼板混凝土浇筑后，需要一定的养护时间才能进行后道工序的施工。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]