[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256300,840,1,"单选题","在双代号网络计划中，如果生产性工作M和N之间的先后顺序关系属于工艺关系，则说明它们的先后顺序是由（ ）决定的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","劳动力调配",false,{"key":16,"text":17,"correct":14},"B","原材料供应",{"key":19,"text":20,"correct":21},"C","工艺过程",true,{"key":23,"text":24,"correct":14},"D","资金需求","双代号网络计划中，如果生产性工作M和N之间的先后顺序关系属于工艺关系，则说明它们的先后顺序是由工艺过程决定的。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]