[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256299,840,1,"单选题","在流水施工方式中，成倍节拍流水施工的特点之一是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一施工过程在各施工段上的流水节拍相等",true,{"key":16,"text":17,"correct":18},"B","同一施工过程在各施工段上的流水节拍不相等，但其值之间为倍数关系",false,{"key":20,"text":21,"correct":18},"C","专业工作队之间的流水步距不相等，但其值之间为倍数关系",{"key":23,"text":24,"correct":18},"D","专业工作队之间的流水步距相等，且等于流水节拍的最小公倍数","其特点是：①同一施工过程在各个施工段上的流水节拍都相等，不同施工过程在同一施工段上的流水节拍之间存在一个最大公约数。②流水步距等于各个流水节拍的最大公约数。③每个专业工作队都能够连续作业，施工段没有间歇时间。④专业工作队数目大于施工过程数目。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]