[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256298,840,1,"单选题","下列市政工程项目进度控制工作中，属于施工方进度控制任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","部署项目动用准备工作进度",false,{"key":16,"text":17,"correct":14},"B","协调设计、招标的工作进度",{"key":19,"text":20,"correct":21},"C","编制项目施工的工作计划",true,{"key":23,"text":24,"correct":14},"D","编制供货进度计划","编制项目施工的工作计划属于施工方进度控制任务。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]