[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256297,840,1,"单选题","以两条以同一开始时间，同一结束时间的”S”形曲线组合而成的进度计划方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":14},"B","前锋线比较法",{"key":19,"text":20,"correct":21},"C","香蕉曲线比较法",true,{"key":23,"text":24,"correct":14},"D","网络图比较法","香蕉型曲线是由两条S形曲线组合而成的闭合曲线。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]