[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256295,840,1,"单选题","在编制工程进度计划后，要计算和绘制劳动力需要量图，它反映了施工期间劳动力的动态变化，是衡量施工组织设计合理性的重要标志。通常评价时所用的指标是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工期间劳动力均匀系数",false,{"key":16,"text":17,"correct":14},"B","施工期间劳动力需要量高峰值",{"key":19,"text":20,"correct":14},"C","施工期间劳动力的平均值",{"key":22,"text":23,"correct":24},"D","施工期间劳动力不均衡系数",true,"编制工程进度计划后，要计算和绘制劳动力需要量图，它反映了施工期间劳动力的动态变化，是衡量施工组织设计合理性的重要标志。通常评价时所用的指标是施工期间劳动力不均衡系数。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]