[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256294,840,1,"单选题","某承包单位在进度计划实施中发现采用的施工技术由于工作面过小而导致进度异常缓慢，也无法投人过多的资源加快施工进度，说明承包商在进度控制中采用的（ ）产生失误。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":18},"B","技术措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","合同措施","施工项目进度控制的措施进度控制的措施包括组织措施、技术措施、经济措施和合同措施等。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]