[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256293,840,1,"单选题","划分（ ）的目的是使各施工队（组）的劳动力能正常进行流水连续作业，以避免出现停歇现象。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程",false,{"key":16,"text":17,"correct":18},"B","施工段",true,{"key":20,"text":21,"correct":14},"C","工作面",{"key":23,"text":24,"correct":14},"D","时间参数","划分施工段的目的是使各施工队（组）的劳动力能正常进行流水连续作业，以避免出现停歇现象。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]