[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256289,840,1,"单选题","下列选项中，不属于施工过程的施工天数估计的依据的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程数量",false,{"key":16,"text":17,"correct":14},"B","资源效率",{"key":19,"text":20,"correct":21},"C","施工顺序",true,{"key":23,"text":24,"correct":14},"D","资源配置","施工天数估计的依据一般包括：a.施工过程的工程量清单。b.资源配置。资源包括人力、材料、施工机械和资金等，大多数情况下，工作持续时闰受到资源分配的影响。c.资源效率。大多数工作持续时间受到所配置的资源的效率的影响。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]