[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256288,840,1,"单选题","工程进度计划比较方法中，主要适用于时标网络计划的方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":14},"B","s形曲线比较法",{"key":19,"text":20,"correct":21},"C","前锋前比较法",true,{"key":23,"text":24,"correct":14},"D","香蕉型曲线比较法","前锋线比较法是从检查时刻的时标点出发，自上而下地用直线段依次连接各项工作的实际进度点，最后到达计划检查时刻的时间刻度线为止，由此组成一条一般为折线的前锋线。通过比较前锋线与箭线交点的位置判定工程实际进度与计划进度的偏差。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]