[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256282,840,1,"单选题","将一般成倍节拍流水施工变为加快成倍节拍流水施工时，所采用的措施为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重新划分施工过程数",false,{"key":16,"text":17,"correct":14},"B","改变流水节拍值",{"key":19,"text":20,"correct":21},"C","增加专业工作队数",true,{"key":23,"text":24,"correct":14},"D","重新划分施工段","将一般成倍节拍流水施工变为加快成倍节拍流水施工时，所采用的措施为增加专业工作队数。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]