[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256281,840,1,"单选题","采用流水作业方式时，劳动力组合应该是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合作业组织形式",false,{"key":16,"text":17,"correct":18},"B","专业分工作业形式",true,{"key":20,"text":21,"correct":14},"C","顺序作业组合形式",{"key":23,"text":24,"correct":14},"D","平行作业组合形式","劳动组织应符合实际情况，流水节拍的取值必须考虑专业队（组）组织方面的限制和要求。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]