[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256276,840,1,"单选题","某段市政道路工程施工，路基填方高度20m，根据进度计划安排，要求路基填筑完成自然沉降半年后，再进行路面施工，则路基填筑与路面施工之间的进度计划搭接关系。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开始到开始",false,{"key":16,"text":17,"correct":14},"B","开始到结束",{"key":19,"text":20,"correct":21},"C","结束到开始",true,{"key":23,"text":24,"correct":14},"D","结束到结束","路基填方高度20m，根据进度计划安排，要求路基填筑完成自然沉降半年后，再进行路面施工，则路基填筑与路面施工之间的进度计划搭接关系结束到开始",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]