[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256274,840,1,"单选题","单代号网络计划中，工作之间的时间间隔等于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","紧后工作最早开始时间减去本工作的最迟完成时间",false,{"key":16,"text":17,"correct":14},"B","紧后工作最迟开始时间减去本工作的最迟完成时间",{"key":19,"text":20,"correct":21},"C","紧后工作最早开始时间减去本工作的最早完成时间",true,{"key":23,"text":24,"correct":14},"D","紧后工作最迟开始时间减去本工作的最早完成时间","单代号网络计划中，工作之间的时间间隔等于紧后工作最早开始时间减去本工作的最早完成时间。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]