[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256273":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256273,840,1,"单选题","工程项目的月进度计划和旬作业计划属于（ ）计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制性",false,{"key":16,"text":17,"correct":14},"B","指导性",{"key":19,"text":20,"correct":21},"C","实施性",true,{"key":23,"text":24,"correct":14},"D","竞争性","工程项目的月进度计划和旬作业计划属于实施性计划。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]