[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256272,840,1,"单选题","最理想的流水施工方式是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","异节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","无节奏流水施工",{"key":19,"text":20,"correct":21},"C","等节奏流水施工",true,{"key":23,"text":24,"correct":14},"D","成倍节拍流水施工","等节奏流水施工是指在有节奏流水施工中，各施工过程的流水节拍都相等的流水施工，也称为固定节拍流水施工或全等节拍流水施工。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]